Hey all
Hope all is well
I am trying to get my head around Lean for process improvement for the first time and attempting to apply Takt time to a service-based industry (end-to-end vocational rehabilitation, so telephone assessment >> work in progress, while medical services arranged, coordinated and monitored >> case closed and final assessment report produced, when individual returns to some form of employment or case is closed).
I don’t think it would be logical to apply takt time to an entire process, as that process (“case”) could be open for 6 months plus? So would it be best to apply takt time to the major operations within the process, essentially just the telephone assessment as I see it?
If my assumption is correct, I would also assume that:
Takt time = 420 minutes (7 hours per day) ÷ number of new referrals for a telephone assessment
Hope all is well
I am trying to get my head around Lean for process improvement for the first time and attempting to apply Takt time to a service-based industry (end-to-end vocational rehabilitation, so telephone assessment >> work in progress, while medical services arranged, coordinated and monitored >> case closed and final assessment report produced, when individual returns to some form of employment or case is closed).
I don’t think it would be logical to apply takt time to an entire process, as that process (“case”) could be open for 6 months plus? So would it be best to apply takt time to the major operations within the process, essentially just the telephone assessment as I see it?
If my assumption is correct, I would also assume that:
Takt time = 420 minutes (7 hours per day) ÷ number of new referrals for a telephone assessment
- Available time – is this based on 1 employee, or would you multiply 420 by the number of staff you have on average? i.e., if you had 5 staff = 2,100 minutes, or is it simply 420 regardless of how many staff you have?
- Number of new referrals for telephone assessment – Assume this would just be based on the average number of referrals received per day?