- Original Poster
- #1
Hi
I'm a plumber (sole trader) who is having issues with a customer.
To cut a long story short, works were agreed with a customer (emailed quote and specification) for a refurbishment of a shower. The costing named the products that were to be installed, which is what the customer agreed to.
After installing the shower tray ready for the next stage of the work the customer contacted me to say they had concerns about the suitability of the tray.
I had specified for a "slim line" shower tray (that's all I ever install). The customer said they felt that the tray needed to be a "deep" tray otherwise there would be the risk of it overflowing!
This is a standard product that is installed every day by many a plumber. At no point during our communication and work did the customer make any specific requests or raise any concerns regarding what was to be installed.
I fully explained in great detail via email (customer refused to answer the phone to me) the differences in slim line tray and that actually the water flows away quicker because the waste/traps you install with them are larger.
The customer wouldn't accept this and said they wanted to get a second opinion. I advised them that this was fine and that I was keen to move forward with the work.
The customer continued to raise various questions about the work via email, which I duely answered, but every time I asked if things had moved forward I was told they had not yet had time and that they still felt the tray wasn't suitable. From this I'm assuming they had not got anyone in to assess the perfectly standard shower tray (or maybe they had!!!)
On a side matter, the customer made comment at various stages of the work about money being tight, and not having any more money. During the work we discovered an unrelated plumbing issue with her water tank in the loft which needed attention. This was fully discussed with the customer and a quote given to rectify this. The customer again said they had no further money until November and asked if I would undertake the additional necessary work, then continue with the shower refurbishment until the work in total reached the initial agreed amount. Then, once they had more money in November, the remaining work on the shower refurbishment could be completed, and the last outstanding sum paid. I agreed to this, and the work proceeded on.
So, after numerous emails I was starting to worry that this was always about not paying, and they have used a ridiculous excuse (the shower tray) in an attempt to do so.
They even made comment in an email that I had pursueded them into the majority of the work, which they didn't need doing in the first place and they were perfectly happy as it was! Which is strange, because if they had looked back over our 30 odd emails they would have seen they had sent me requests off their own back for items they were interested in etc. taking a very active role in the specification that was to be agreed.
18 days had passed since they had contacted me about the shower tray concerns, with still way forward despite my attempts.
I would just just like to add, the shower tray is completely fine and fit for purpose.
So, with the added concerns about getting paid I have sent them an invoice for the work undertaken to date, including all the supplied items etc. Givening them 14 days to pay. I also explained that I was more than happy to continue with the work, but would like the invoiced settled before continuing with any further work. Which was pretty much agreed with them before them the additional required work came to light.
They had previously had a full detailed cost breakdown from me (individual labour and material charges), so they knew exactly what had been spent to date.
Follwing the invoice they replied by saying that they are still not happy with the tray, although they are still not advising what action if any has been taken by them, and that they would not pay me until all the work was complete. Which is actually contrary to our second agreement of stopping at the first agreed figure.
I'm not sure what else I can do to move things forward? I feel like they are purposely dragging their heals.
Where do I stand legally with issuing the invoice despite the agreed work not yet being complete?
Plus, I don't want to lift another tool in their house until I see the money due?
Is this the sort of situation that ends up in the small claims court? (Never had the experience)
Any advice and help would be greatly appreciated.
I'm a plumber (sole trader) who is having issues with a customer.
To cut a long story short, works were agreed with a customer (emailed quote and specification) for a refurbishment of a shower. The costing named the products that were to be installed, which is what the customer agreed to.
After installing the shower tray ready for the next stage of the work the customer contacted me to say they had concerns about the suitability of the tray.
I had specified for a "slim line" shower tray (that's all I ever install). The customer said they felt that the tray needed to be a "deep" tray otherwise there would be the risk of it overflowing!
This is a standard product that is installed every day by many a plumber. At no point during our communication and work did the customer make any specific requests or raise any concerns regarding what was to be installed.
I fully explained in great detail via email (customer refused to answer the phone to me) the differences in slim line tray and that actually the water flows away quicker because the waste/traps you install with them are larger.
The customer wouldn't accept this and said they wanted to get a second opinion. I advised them that this was fine and that I was keen to move forward with the work.
The customer continued to raise various questions about the work via email, which I duely answered, but every time I asked if things had moved forward I was told they had not yet had time and that they still felt the tray wasn't suitable. From this I'm assuming they had not got anyone in to assess the perfectly standard shower tray (or maybe they had!!!)
On a side matter, the customer made comment at various stages of the work about money being tight, and not having any more money. During the work we discovered an unrelated plumbing issue with her water tank in the loft which needed attention. This was fully discussed with the customer and a quote given to rectify this. The customer again said they had no further money until November and asked if I would undertake the additional necessary work, then continue with the shower refurbishment until the work in total reached the initial agreed amount. Then, once they had more money in November, the remaining work on the shower refurbishment could be completed, and the last outstanding sum paid. I agreed to this, and the work proceeded on.
So, after numerous emails I was starting to worry that this was always about not paying, and they have used a ridiculous excuse (the shower tray) in an attempt to do so.
They even made comment in an email that I had pursueded them into the majority of the work, which they didn't need doing in the first place and they were perfectly happy as it was! Which is strange, because if they had looked back over our 30 odd emails they would have seen they had sent me requests off their own back for items they were interested in etc. taking a very active role in the specification that was to be agreed.
18 days had passed since they had contacted me about the shower tray concerns, with still way forward despite my attempts.
I would just just like to add, the shower tray is completely fine and fit for purpose.
So, with the added concerns about getting paid I have sent them an invoice for the work undertaken to date, including all the supplied items etc. Givening them 14 days to pay. I also explained that I was more than happy to continue with the work, but would like the invoiced settled before continuing with any further work. Which was pretty much agreed with them before them the additional required work came to light.
They had previously had a full detailed cost breakdown from me (individual labour and material charges), so they knew exactly what had been spent to date.
Follwing the invoice they replied by saying that they are still not happy with the tray, although they are still not advising what action if any has been taken by them, and that they would not pay me until all the work was complete. Which is actually contrary to our second agreement of stopping at the first agreed figure.
I'm not sure what else I can do to move things forward? I feel like they are purposely dragging their heals.
Where do I stand legally with issuing the invoice despite the agreed work not yet being complete?
Plus, I don't want to lift another tool in their house until I see the money due?
Is this the sort of situation that ends up in the small claims court? (Never had the experience)
Any advice and help would be greatly appreciated.
