- Original Poster
- #1
I have recently started a self build and have cut through a 33000 v electricity cable, im lucky to be alive. I have had the electricity people over for the last 5 days digging the cable up as they have to replace a large section of it. They say probably 3 weeks in total and will cost me around £250,000. I have full planing permission to build on the land. We had footings in which were 1msq however the building inspector did not aprove them so we had to take them out and dig down 1.5m and this is when we hit the cable. There are 4 cables running under the proposed building site.
The engineer from the electricity board has told me that I will not be able to build on the site. I have told him to send this to me in black and white.
With regards to the legal side of this, is the building inspector supposed to request a land survey before we start digging. Im not a builder and do not have insurance for this so where do I stand, I really need some good advice.
The engineer from the electricity board has told me that I will not be able to build on the site. I have told him to send this to me in black and white.
With regards to the legal side of this, is the building inspector supposed to request a land survey before we start digging. Im not a builder and do not have insurance for this so where do I stand, I really need some good advice.
